The short answer

Often not, on a house in England, as long as the unit heats as well as cools and meets the limits below, including a 37 dB noise test at your neighbour’s window. Listed buildings, cooling-only units, and shops and offices are different.

About 3 minutes to read5 sources, named belowA quick planning check insideChecked 5 November 2026

On this page
  1. What changed in May 2025
  2. The limits on a house or a block of flats
  3. The 37 dB noise test
  4. Cooling-only units
  5. Shops and offices
  6. The Cotswolds and north Wiltshire
  7. If you want it in writing

A quick check. Not legal advice.

Is the building listed, or is the unit going in the grounds of a listed building?

What changed in May 2025

Since 29 May 2025, air conditioning that can heat as well as cool has been able to count as an air source heat pump under Class G of Part 14 of the General Permitted Development Order. That is a national planning permission, so if a unit meets every limit, you don’t need to apply. The same change removed the old rule that kept units a metre from the boundary.

The limits on a house or a block of flats

  • One outdoor unit on a terraced or semi-detached house or a block of flats. Up to two on a detached house. A block must be wholly flats: one with shops or offices in it doesn’t count.
  • The outdoor unit, with its housing, no bigger than 1.5 cubic metres on a house, or 0.6 on a block of flats.
  • Not on a pitched roof. On a flat roof, at least a metre from the edge.
  • Not on a listed building or in its grounds, and not on a scheduled monument.
  • In a conservation area or World Heritage Site, not on a wall or roof that fronts a road, and not nearer any road around the property than the house itself.
  • Everywhere else, not on a wall fronting a road above ground-floor level.
  • It must not be used solely for cooling, and it must be sited, so far as practicable, to minimise its effect on appearance and on the area.
  • There must be no wind turbine already on the building or in its grounds.

The 37 dB noise test

The unit must also pass the MCS 020 a) calculation, explained in how noisy air conditioning is, whether or not your installer is MCS certified. The sound at a point one metre out from your neighbour’s nearest habitable window must come to 37 dB or less. Many pages still quote 42 dB: that was the old method. Hedges and open fences don’t count. A solid wall or fence that hides the unit does.

Sound power of the outdoor unitBracketed high on one wallOn the ground against a wallAs before, behind a solid screen
57 dB4.0 m5.6 m1.8 m
59 dB5.0 m7.1 m2.2 m
60 dB5.6 m8.0 m2.5 m
Roughly how far a unit needs to be from that window. Our arithmetic from the MCS formula, for illustration only: a real survey uses the MCS table and the actual model.

Cooling-only units

These fall outside Class G. The government said in June 2026 that planning permission usually isn’t needed for a small home where the unit doesn’t materially change the outside of the building, that there’s no blanket rule, and that you should check with your council.

Shops and offices

There’s no equivalent national permission for air source units on business premises. Whether you need to apply depends on whether the unit materially affects the outside of the building, which is for the council to judge. Councils do enforce this, particularly in conservation areas.

The Cotswolds and north Wiltshire

Class G names conservation areas and World Heritage Sites, but not National Landscapes, so being in the Cotswolds National Landscape doesn’t by itself remove the right. Stonehenge and Avebury are a World Heritage Site in Wiltshire, so the stricter rule applies there. Councils can also remove these rights with an Article 4 direction or a planning condition, so check your property.

If you want it in writing

You can apply to your council for a lawful development certificate, which confirms that a proposal doesn’t need a planning application. We look at all of this before we quote.

This is a plain summary for England, not legal advice. Wales and Scotland have their own rules.

Sources

  1. Part 14, Class G, General Permitted Development Order 2015
  2. The 2025 amendment, SI 2025/560, in force 29 May 2025
  3. MCS 020 a), the planning noise standard
  4. MHCLG statement on air conditioning rules, 25 June 2026